    Dynamic action working for change but not create even when I use code 06

    Paddy Srinivas

      I have created a dynamic action from IT 0000 to call a custom program and then populate IT 0003-BDERR date with the RP50d-date1 returned from the custom program.

      My dynamic action is working fine and updates IT 0003 when IT 0000 is changed, but is not working when IT 0000 is created. I am using code 06 (create and change).

      I debugged through the program and the program populates the date RP50D-Date1 correctly in both cases (create and change).  But somehow, IT 0003 is updated only when IT 0000 is changed. 

      Could you please tell me what is wrong?