1 Reply Latest reply on Jun 16, 2014 10:47 PM by Matthew Bertino

    Quantity Contract options

    William Johnson
    Visibility: Open to anyone

      My company currently does quantity contracts based on product Hierarchy manually today.  I know that you can only do that with Value contracts in SAP but was wondering if anyone has done either customizations or other enhancements with quantity contracts.

       

      We are in the construction industry and all of our contracts are done this way since jobs are done at a high level and not until later in the job are the items sold with specific materials.

       

      We just started the build phase of our project so we have not gone live yet.

       

      Thanks.

       

      Bill Johnson